Upcoming Work

Works on the main build of SQP1 are progressing well. In the foreseeable future we will continue working on our core and superstructure slabs construction, facade, M&E and internal fit-out. 

In the next few months we have the following coming up: 

Core construction

Our core construction will continue till Q2 1019. We currently working to a 12-working day cycle for every 1.5 floors.

Superstructure slab construction

Superstructure slab construction will also continue for the foreseeable future. We are currently working to a 10-working day cycle for every floor of slab construction, including both the South and North towers of SQP1.

Façade install

Works on the facade are progressing well and will be continuing to follow our core and slabs approximately 10-15 levels behind.

Internal fit-out

Internal fit-out commenced earlier this month and will continue for the foreseeable future.

We are currently working on our first fix and second fix will commence in the next few weeks.

Bathroom pod deliveries

In order to minimise our impact on the environment and local community, reduce our waste and time on site, we are utilising pre-fabricated bathroom pods. These come on wagons, which are unloaded on site and vertically transported to the required floor.

Bathroom pods are closely following our slab construction and are brought up the building pre-facade install.

M&E

M&E is another ongoing aspect of our construction progress.

Upcoming works are from the FED to the newly delivered MUC's that are produced of site and delivered complete to reduce install time.

Crane climbs

We have still got a number of crane climbs to complete. We will be informing you of when these will be in a timely manner and allowing to express any concerns if you have any.

The entire Berkeley team cannot thank you enough for your understanding and support during the weekends we have had to work in order to make these crane climbs happen.

Dock drainage works

We have recently welcomed Dyer & Butler onto site, who will be completing our dock drainage works.

Works are due to commence in the very near future and will continue for approximately 12 weeks.

Landscaping

Phase 1 of our landscaping works will commence on shortly after our dock drainage works are complete. We are aiming to complete these works by early Q1 2019.

If you have any questions or concerns regarding our upcoming works, please do not hesitate to Contact Us.