Upcoming Work

Main activities on site continue to be building the basement raft for our building. As such, this mainly involves concrete pouring various sections of the deepest and most complicated for this part of the job B2 basement slab.

With the already erected in January TC1 and the upcoming erection of TC2 we are looking to have a good progress in the next few months with completing in full the basement 2 and Basement 1 levels.

Together with this, we will be starting the building's 220m tall concrete lift shaft core, where once the construction of the vertical elements passes ground level, we would be looking to fully complete and close in the Ground Floor slab. This will be a milestone in the project, as would lead and open the front for the next construction stages in the upcoming months.