Works and Progress

Progress update

Work to the site continues to progress well on the main build for SQP1.
We are currently working on completing concrete works on our  basement levels, alongside assembling panels for our jumpform.

Tower Crane Erection

Following the successful erection of TC1 in January, in April 2017 we welcomed TC2 onto site.
Currently TC1 and TC2 stand at 80.35m and 92.35m respectively and will reach 242.35m and 234.35m by the end of the project.

Bulk Earthworks & B2 slab

We have now completed our bulk earthworks and consequently our B2 slab.
The majority of our bulk earthworks were done via a barge. We utilised a total of 31 barges preventing 3,850 vehicle movements along Marsh Wall.

DDE Access Road

We are very happy to announce that we have almost completed our basement works, allowing us to establish a new DDE access road.
Thank you very much for your cooperation during this phase of works.

Temporary Electrics

The SIDU has now been energised. TC1 and TC2 have been made live, allowing the removal of both of their independent generators.
We are also aiming to have live temporary electrics in the welfare facilities by mid-July.

Planting Raspberries

We have also spent some time thinking about the environment and how we can contribute. We have planted 7 canes of raspberries on the patio of our project office and are planning on expanding this initiative by planting some chillies and other small herbs.